Update situation Le Valais - as of August 7, 2024

As of August 7, 2024

Restoration efforts for our infrastructure, machinery, and equipment are progressing as planned. Fine cleaning and drying remain top priorities to ensure optimal conditions when operations restart. As of today, we continue to have the assistance of 150+ third-party specialists and more than half of the estimated fine cleaning operations are complete.  

Initial diagnostics from the manufacturers of critical machines are mostly positive, though some require more complex restoration plans. Our main objective now is to ensure necessary repair plans are carried out swiftly and thoroughly by closely collaborating with the manufacturers.

Our on-site teams are working diligently on the key priorities outlined in the recovery plan, and we are deeply grateful for their hard work. We continue to do our utmost to get back up and running as soon as possible and are committed to limiting the impact on our stakeholders served by these facilities.